Check mains power supply including charging rates (where applicable).
Check battery power supply including charging rates (where applicable).
Check satisfactory operation.
Cleaning control components.
Check operation of all system components.
Log all test results
Retrain the users on the use of the system (if required)
Fire Alarm System
Check the graphic command centre PC for proper operation, communication errors, check operating system & data files, verify the operation of the printer.
The alarm function of the control panel shall be checked by means of a trigger device in each zone.
All auxiliary function of the control panel shall also be tested where practical and rectify the faults of Control Panel’s for physical damage, indicators etc.
All fault indicators and their circuits shall be checked preferably by simulation of fault conditions.
The control and indicating equipment shall be cleaned and faults rectified at each visit.
All connections shall be examined to intact and free from any sort of dust, corrosion, etc.
Exit & Emergency Light System
Visual Inspection to ensure that exit & emergency light were installed & distributed on all the areas where it is required.
Ensure that all the ELCB assigned to Emergency & Exit lights were properly identified.
Switch off the main supply to ensure that all the Emergency & Exit lights was illuminate with battery for at least 2 Hours.
Inspect the lights visually whether the luminance is sufficient for the areas.
For the Central Battery System, Battery voltage & charging voltage will be checked.
Fire Pump System
Check line pressure/gauges/pressure switches and valve condition.
Visual inspection of pump room pipe work joint and fitting for leakage.
Check Corrosion.
Check the pressure switch array and correct operation of Main & Jockey pumps.
Activate electric pump, check start sequence.
Activate diesel pump, check start sequence and temperature (Where fitted), Shutdown mechanism, check the batteries, charger, water and fuel level.
Logging of pumps.
Operate the pump.
Inspect tightness of foundation and hold-down bolts
Check pumps alignment, coupling conditions and integrity.
Check for unusual noise, vibration, temperature, leaks
Check that drain lines are working properly
Add grease to pump anti-friction bearings
Check wiring or loose or hot connections
Clean and lubricate gland bolts
Check service Motor starter contacts
Verify free movement of packing glands
Check and flush seal water and drain piping
Performa comparative field test (flow, pressure and power) with calibrated instruments
Inspect sleeves.
Verify if worn
Check pumps and prime movers operation inclusive of controls.
Lubrication of mechanical parts.
Response to pumps, i.
e., when open operated pumps should start automatically.
Response to fire panel.
Sprinkler System
Check that all sprinkler piping in pump rooms and on services floors are not leaking and there is no visual mechanical damage.
Ensure that the main valves are in open position and secure with padlock and leather strap.
Check that the quantity of spare sprinkler heads is correct.
Check motor alarm by operating testing valves in sprinkler control rooms.
Operate sprinkler pumps and starters by operating of flow switch.
Flow of water through system.
Inspect sprinklers to make sure they are free of corrosion, obstructions to spray pattern, foreign materials, paint and physical damage.
All subsidiary control valves served individual floors should be checked to make sure that they are functioning properly and are not unintentionally closed.
Zone Control Valve Checking.
Deluge System
Check foam concentrate line valves.
Check water inlet line valves.
Check foam level in the tank.
Check control valve is in the open position and monitored.
Make sure drainage is adequate.
Test water flow alarm by opening the alarm by-pass
Check nozzles for blockage & sprinkler positioning.
Response to fire alarm system
Inspection of valves, switches.
Check for any water leakages.
Inspect the deluge valves to make sure: valves are free from damage, no water leakage, no any rusting.
Take necessary action if there is any deficiency.
Inspect the piping and sprinkler for any corrosion, any foreign materials or any physical damage.
Take necessary actions accordingly.
Inspect the gauges and make sure they’re in good condition, record the pressure.
Check and test activation procedure of extinguishing panel, batteries and test connected devices.
Pre-action System
Check concentrate line valves.
Check water inlet line valves.
Check foam level in the tank.
Check control valve is in the open position and monitored.
Check nozzles for blockage & sprinkler positioning.
Response to fire alarm system.
Inspection of valves, switches.
Check for any water leakages.
Foam System
Check the physical condition of the containers.
Check the pressure, cylinder’s body and paint condition
Check the heap cap assemblies and valves operation